"id": "P3.1",
|
|
"name": "规划进度管理",
|
|
"processGroupId": "PG02",
|
|
"processGroupName": "规划过程组",
|
|
"purpose": "为如何在整个项目期间管理项目进度提供指南和方向。本过程仅开展一次或仅在项目的预定义点开展。"
|
|
},
|
|
{
|
|
"id": "P3.2",
|
|
"name": "定义活动",
|
|
"processGroupId": "PG02",
|
|
"processGroupName": "规划过程组",
|
|
"purpose": "将工作包分解为进度活动,作为对项目工作进行进度估算、规划、执行、监督和控制的基础。本过程需要在整个项目期间开展。"
|
|
},
|
|
{
|
|
"id": "P3.3",
|
|
"name": "排列活动顺序",
|
|
"processGroupId": "PG02",
|
|
"processGroupName": "规划过程组",
|
|
"purpose": "定义工作之间的逻辑顺序,以便在既定的所有项目制约因素下获得最高的效率。本过程需要在整个项目期间开展。"
|
|
},
|
|
{
|
|
"id": "P3.4",
|
|
"name": "估算活动持续时间",
|
|
"processGroupId": "PG02",
|
|
"processGroupName": "规划过程组",
|
|
"purpose": "确定完成每个活动所需花费的时间量。本过程需要在整个项目期间开展。"
|
|
},
|
|
{
|
|
"id": "P3.5",
|
|
"name": "制订进度计划",
|
|
"processGroupId": "PG02",
|
|
"processGroupName": "规划过程组",
|
|
"purpose": "为完成项目活动而制定具有计划日期的进度模型。本过程需要在整个项目期间开展。"
|
|
},
|
|
{
|
|
"id": "P3.6",
|
|
"name": "控制进度",
|
|
"processGroupId": "PG04",
|
|
"processGroupName": "监控过程组",
|
|
"purpose": "在整个项目期间保持对进度基准的维护。本过程在整个项目期间开展。"
|
|
}
|
|
]
|